TIMIMOUN

Project

1
 
Market
2
 
Client
3
 
Location
4

DORIS delivered a range of services including basic engineering and preparation for calls for tenders.

Project outline

This plant is fed by 14 gas producing wells drilled before plant start-up and 23 extra wells drilled later. The gas is collected via 5 clusters, provided with production and test manifolds, and sent through trunklines to the Central Processing Facility to be treated. The CO2 content in the raw gas (7%) is eliminated through an amine unit and re-injected in 2 disposal wells. Treated gas is exported through a 24’’ pipeline up to a tie-in point to a new pipeline to be installed as part of another project.

  • Onshore Gas Plant
  • Production : 5 Million m³ gas /day
  • Central Processing Facilities : 740,000 m²
  • Accommodation Camp : 200 persons, 72,000 m²
  • Airstrip for BEECH 1900 D airplane
  • 313 km of pipelines
  • 5 clusters collecting gas from wells
  • 37 gas wells
  • 2 CO2 injection wells

Services delivered by DORIS

Across the 42,000 manhour project, DORIS delivered the:

  • Optimization of the Pre-Project Dossier
  • Basic Engineering of the Facilities including Project Management, Coordination and Services to Company
  • Preparation of Technical Consultation Dossier for Long Lead/Critical Items
  • Preparation of Call for Tender Dossier for AGRU licenses services
  • Preparation of Call for Tender for 3 EPC Contracts (CPF and off-sites, accommodation camp, site preparation and main access road)

Our Projects

Trion

Trion field

DORIS delivered SURF and Export Pipeline Pre-FEED and SURF FEED to this project. Project outline The...
Read More
Repsol

Block 29 Conceptual Engineering

DORIS delivered Conceptual Engineering for the Subsea Production System (SPS) & Subsea Umbilical,...
Read More
Sanaga

Sanaga

Across this FEED scope, DORIS achieved 10% cost saving compared to pre-FEED Project outline The Cameroon...
Read More