NSIKO & BONGA SWA

projects

DORIS performed pre-FEED study of stand-alone FPSO developments for Nsiko and Bonga SWA

DORIS conducted a conceptual/pre-FEED level development study of two new oil discoveries in order to 1) establish technical feasibility and help the client establish commercial feasibility and 2) perform pre-FEED level engineering to facilitate the client’s discussions with their joint venture partner.

Options studied included:

  • Stand-alone FPSO developments for Nsiko and Bonga Southwest/Aparo
  • Long-distance subsea tiebacks from one field to the other
  • Dry tree and FPU-based developments for Nsiko
  • Co-development versus phased development

Subsequent to the initial study, DORIS was again contracted to conduct a full pre-FEED study of the NSiko subsea system.
This work entailed extensive steady-state and transient flow assurance, flowline mechanical design and insulation specification, and equipment/controls/distribution system analysis and preliminary design.

Services provided by DORIS:

Concept identification / development / feasibility, including:

  • Field architecture
  • Transient and steady-state flow assurance and operability
  • Flowline specification (size and insulation)
  • Topsides HYSYS modeling, heat and material balances, equipment sizing
  • Topsides equipment layouts on FPSO, FPU, TLP
  • Detailed capital cost and schedule estimates for all scenarios
  • Capital cost benchmarking
NSIKO & BONGA SWA

Main characteristics:

  • Water Depth: 1200 to 1800m
  • Production Facilities: Subsea wells to local & remote FPU’s (purpose build FPSO, or Semi-submersible)
  • Oil Production: Up to 200,000 bopd & 300MMscfd
  • No. ofWells: Up to 60 subsea wells
  • No. of Drill Centers: 15
  • Tieback Distance: Up to 10km when local to FPSO & 20 km to remote host
  • Project