MOHO-BILONDO Phase 1bis

projects

DORIS team was integrated in Total’s SPS Package Management Team to manage the SPS Contractor

 

The Moho Nord joint development project includes two field developments, namely Moho Nord and Moho Bilondo Phase 1bis.

Phase 1bis is a subsea tieback to Moho Bilondo FPU. It targets additional reserves in the southern portion, whereas Moho Nord surface facilities (new FPU & TLP) gather the reserves from the northern portion of the licence area.

Services provided by DORIS:

  • To ensure compliance of detailed engineering deliverables with TEPC needs and Interfaces requirements from the other packages (UFR, FPU & Drilling)
  • To follow up the manufacturing and Factory Acceptance Test of all SPS Equipments
  • To prepare and run the Control System EFAT with involvement of the Field Operation team
  • To prepare and run EFAT & SIT of Production Manifold System at construction yard
  • To prepare and run the control system pre-commissioning on the FPU and subsequent assistance to the field operation team for the commissioning and start-up offshore
  • To perform Schedule Risk Management to deliver all the SPS Equipments on time
  • To prepare the handover of the Project to the affiliate in Congo
MOHO-BILONDO Phase 1bis

Main characteristics:

Locations / Sites : Norway, UK, Korea & Congo
Production XTs : 18 off (1bis: 7; MHN: 11)
Water Injection XTs : 10 off (1bis: 4; MHN: 6)
IWOCS : 2 off
Production Manifolds : 6 off (1bis: 2; MHN: 4)
Production Jumpers : 18 off (1bis: ; MHN:11)
Topside Control System : 1 for Phase1bis & 1 for Moho Nord
First Oil Phase 1 Bis: December 2015
First Oil Moho Nord: March 2017

 

 

 

 

 


20,000 manhours